top of page

CAMELLIA

Allgood worked with Odyssey Engineering Group, to develop the utilities and pavement for Camellia Section 2 consisting of 24,000 Square Yards of Pavement, 5,500 Feet of Water Line, 7,000 Feet of Sanitary Line, and 5,000 Feet of Storm Sewer.  Odyssey Engineering wanted to incorporate a delayed drainage system, that allowed the subdivision streets to be free of standing water during a heavy storm. The use of a focal point system consisted of six detention ponds throughout the section. These ponds were landscaped and constructed to hold water over a short period of time, allowing the street runoff to retain into the pond while the pond had a delayed drainage to its nearest water source. The detention ponds and street excavation consisted of over 62,000 Cubic Yards that were all hauled offsite accordingly. Total Project Duration, 365 Days.

CAMELIA COVER PHOTO.JPG
bottom of page