WALNUT CREEK

Allgood has completed the paving construction for four sections within the newly developed Walnut Creek Subdivision, including Section 14, 17, 20, 21, and a Collector Road providing an additional entrance from the south side of the subdivision. Working alongside IDS Engineering Group, the four developments combined for over 36,000 Square Yards of pavement, with the over 5,000 Feet of Sidewalk. By use of our equipment’s satellite surveying ability, we were able to quickly excavate, haul, and grade nearly 20,000 Cubic Yards  and over 200 lots. This development was completed over a combined project length of 180 days.

WALNUT CREEK COVER PHOTO.JPG